PhET Progress Report
June 28, 2007
An online version of this report is available here.
Here’s a pie chart representation of the time distribution.
Sim Installers
· Worked in collaboration with John.
· First draft complete, see example installers (windows):
o CCK AC
· To build installers for all (approx 49 including some tests) simulations takes about 30 minutes. This process is fully automated (except for manual testing afterwards)
· The installers for windows + mac + linux takes up about 440Mb.
·
Remaining
work:
o
Cleanup
code
o
Bundled
JRE for windows version
o
Error
handling for JRE autodetect failure
o
Icons for
each simulation
o
Icons on
mac
o
Mac files
should be zipped
o
Jar files
should have the right name
o
More
thorough testing
Motion
· Finished handling for offsets due to numerical derivative
· Automated tests to ensure correctness
· Bugfixes
· Many of these changes can be seen in a mock-up of the moving man simulation
· Here is a more fine-grained list of work on the motion project
· Work here is essentially complete, except for cleanup and issues that arise with integration into the rotation simulation
Interview
· Attended candidate’s talk
· Interview with candidate & writeup comments
Misc
· Emailed Wolfgang Christian about advertising & community benefits (haven’t heard back yet)
· Added speed & height readouts to Energy Skate Park
·
Discussion
of ideal-gas; band-aids vs. surgery
Upcoming Work
· Rotation/Torque (with John)
· Time Series
· Physical model (with correct offsets in derivatives)
· Charts (with correct layering for data series?)
· Licensing issues/Meet with Kate Tallman?
· GUI for translation system
· CCK
· remove old CCK, upgrade to CCK DC Only version after some small fixes