PhET Progress Report

Sam Reid

Feb 11, 2009

 

An online version of this report is available here.

Hereís a pie chart representation of the time distribution.

 

Ladybug

         Deployed 1.20.29 with about 40 changes since last week

         Currently 6 issues remain in the to-do document

         About 60 hours of my time so far

 

Translations

         Identify and implement temporary workaround for translation-deploy process

         Recommended postponing deploy of further translations until IOM sims are out (would take 2-3 hours and increase build complexity to resolve this otherwise).

 

Misc

         Reorganize repository so build-tools is global instead of just accessible by java sims

         Improved flash build support in PBG

         IDE bug reports and updates

         Discuss IOM tickets, esp. privacy dialog

         Renamed ohm1d to battery-resistor-circuit

 

Questions

         What is the status of credits.txt?

         Report generation with sample data?

         What else is necessary before we can alpha test everything for IOM?

         If alpha test is successful, what else will be necessary before beta test?

 

Upcoming Work

         Issues for 3/31/2009 Milestone

         Motion series suite, including Ladybug 2D

         For details, See ticket report "Sam R: Report" here and the google doc linked above