PhET
Progress Report
Sam
Reid
Feb 11,
2009
An
online version of this report is available here.
Here’s
a pie
chart representation of the time distribution.
·
Deployed 1.20.29 with about 40 changes
since last week
·
Currently 6 issues remain in the to-do
document
·
About 60 hours of my time so far
Translations
·
Identify and implement temporary workaround for
translation-deploy process
·
Recommended postponing deploy of further
translations until IOM sims are out (would take 2-3 hours and increase build
complexity to resolve this otherwise).
Misc
·
Reorganize repository so build-tools is global
instead of just accessible by java sims
·
Improved flash build support in PBG
·
IDE bug reports and updates
·
Discuss IOM tickets, esp. privacy dialog
·
Renamed ohm1d to battery-resistor-circuit
Questions
·
What is
the status of credits.txt?
·
Report
generation with sample data?
·
What
else is necessary before we can alpha test everything for IOM?
·
If
alpha test is successful, what else will be necessary before beta test?
Upcoming
Work
·
Issues
for 3/31/2009 Milestone
·
Motion
series suite, including Ladybug 2D
·
For
details, See ticket report "Sam R: Report" here
and the google doc linked above